Stay informed with the latest construction updates on Brook.
CONSTRUCTION
Brook Village currently has 283 houses under construction and 324 completed houses.
Construction refers to the number of houses completed or under construction.
Construction update photo as of Q1 2025
SITE DEVELOPMENT
Site development of Brook is at 99% completion.
Site Development covers site clearing, grading, roads, utilities, open parking, and related work.
Construction update photo as of Q1 2025
AMENITIES
Ongoing construction of the of Play Equipment and Street Signages are scheduled for completion in Q1 2025.
Amenities include the completion of the clubhouse, pools, function areas, parks, playgrounds, courts, guardhouses, landscaped spaces, and equipment rentals.
Construction update photo as of Q1 2025
VECINO TURNOVERS
In Brook, 111 houses and lots were turned over, along with 68 lot-only units.
Vecino Turnovers are residential lots and houses that have been turned over to vecinos. The Turnover Office is open to serve vecinos for acceptance and turnover activities. Turnover Office Hours: 8:30 AM – 5:30 PM.
VALUE APPRECIATION
Brook enjoys positive returns at 157% value appreciation since its launched in 2019.
Value Appreciation indicates the increase in property value since the launch year.
SALES
There are currently 76 units in Brook that are available.
Sales represent the available inventory for the quarter.
The general updates from Aboitiz Land are intended for informational purposes only and are subject to change without prior notice. For individual unit status, refer to the Vecino App or contact our Customer Service team at aboitizland.customer.service@aboitiz.com.
We use cookies to improve your experience on https://www.thevillagesatlimaestate.com.ph. Click “I accept” to let us know you’re okay with our cookie policy. Find out here.